Montague WWTP Upgrades
2020/2021
Upgrades to the Montague Wastewater Treatment Plant began in October of 2020. The purpose of the upgrades is to increase storage for bio-solids and increase capacity for treatment through aeration and automated process control. The following work has been completed or is currently underway:
- Concrete bio-solids tank construction is complete.
- Underground pipework is under construction.
- Upgrades to control building (doors/electrical/ventilation) under construction.
After completion of these phases, next phases will include:
- Upgrades to the aeration piping, with new blowers.
- Installation of a SCADA (Supervisory Control and Data Acquisition) system for the WWTP to optimize operations.
- New fencing, landscaping including the addition of trees for aesthetics.
Construction is expected to be complete in early spring of 2021